For a number of years the roof in our church has been a problem in the wet weather. Remedial work was carried out but expert analysis confirmed that there was a big problem with the timber under the copper. Further analysis revealed that chipboard was used under the copper, and that this had rotted with moisture over the years. Given the wide span in the church roof, copper was used as the material on the roof when the church was built. It was decided earlier this year to replace the copper roof as well as the timber underneath. The new roof would have superior timber to withstand moisture as well as insulation and special roofing felt.
The second problem to be addressed was drainage in the church grounds where water ponding was occurring during periods of wet weather. Investigations revealed that many of the old clay pipes had collapsed and needed to be replaced. New kerbing and drainage of surface water was also required.
Thirdly, the paving around the church was regarded as being unsafe for pedestrians, with many old flagstones unstable and uneven. A new paved brick entrance to the Church is also incorporated in the works.
The project began in early September 2009 and the roofing part of the project was complete by the end of October 2009, thanks to the great spell of dry weather. The drainage and paving aspect of the project will be complete by Christmas 2010. The completed works promise to enhance our beautiful church and to the safety around the grounds also.
Despite the recession, our parishioners have been very generous and very supportive of this building project. Many thanks to all who have supported this major refurbishment through the weekly envelope collection and through the very successful Parish Draw in May 2009.